474 GW is a count of requests, not of load: more than 1,800 projects, about 90% of them data centres, adding up to more than five times the record peak. When holding a place in a queue costs little next to the size of the claim, the queue measures how cheap it is to ask, and speculative requests pile up beside real ones.
The audit (about 300 sites of 75 MW or more, results due 10 December) is the right move, but the useful output isn't a smaller total. It's two numbers a reader can reuse:
- The queue by stage: requested, studied, signed, energised. 474 GW is only the first.
- The conversion rate: what share of past requests was ever energised. That turns the headline into an estimate.
Without a price on holding a place, such as a deposit or milestone that scales with the megawatts claimed, an audit cleans the queue once and it refills. A freeze buys time; pricing the request is what fixes the count.